Frequently Asked Questions
Learn more about the MariBell Transmission Project
An electric transmission system is what we often call the grid. It carries electricity over long distances to power homes, farms and businesses. The proposed MariBell Transmission Project will strengthen the Upper Midwest grid, helping ensure reliable, cost-effective energy for families and communities across Minnesota and Wisconsin.
Ask our
Team
The MariBell Transmission Project is an approximately 140-mile, 765/161 kV proposed double-circuit transmission line that would be built between Marion, Minn., and Bell Center, Wis. The proposed transmission line would span portions of Olmsted, Mower, Fillmore and Houston counties in Minnesota and Vernon and Crawford counties in Wisconsin.
The segment is part of a larger North Rochester – Columbia transmission project that was approved by the Midcontinent Independent System Operator (MISO) in December 2024. The MariBell Transmission Project will enhance the reliability and resilience of the regional electric grid, help meet surging energy demand and support the region’s growing economy.
In December 2024, MISO identified and approved a portfolio of transmission projects in its Long Range Transmission Plan that are needed to enable the grid of the future — boosting reliability, providing access to cost-effective energy resources and meeting growing energy demand. The MariBell segment is among the projects included in the plan.
MISO is the regional grid operator responsible for ensuring power flows reliably across 15 states in the central United States and the Canadian province of Manitoba.
Overall, the proposed transmission project would increase the ability to transfer power between Minnesota and Wisconsin, unlock access to more energy resources and enable a reliable grid for the future.
Xcel Energy is developing approximately 35 miles of a new single-circuit 765 kV transmission line that will run from the North Rochester Substation near Pine Island to Marion, Minn. Dairyland Power Cooperative and GridLiance Heartland are developing the MariBell segment of the project, which will extend from Marion, Minn. to the Mississippi River. This segment will replace an existing 161 kV transmission line with a new 765/161 kV double-circuit transmission line.
Yes, Dairyland Power Cooperative and GridLiance Heartland are engaged with relevant federal, state and local regulatory agencies to ensure the project is designed, constructed and operated in compliance with applicable laws, regulations and management policies.
We are committed to environmental protection and stewardship. We conduct rigorous environmental analyses to ensure we appropriately locate transmission lines and implement best practices to limit our impact on wildlife, sensitive habitats and other natural resources as well as Tribal, cultural and historic resources. We incorporate siting and design features to minimize impacts to sensitive viewsheds.
Formal comments regarding the MariBell segment of the Gopher to Badger Link and its regulatory filings can be submitted directly to the Minnesota Public Utilities Commission in accordance with its schedule and procedures:
Minnesota Public Utilities Commission (MPUC)
Dairyland Power Cooperative will submit a Certificate of Public Convenience and Necessity (CPCN) application to the Public Service Commission of Wisconsin (PSCW) for the MariBell Transmission Project this winter.
Landowners along the proposed route can continue to contact the land agent they are working with or contact the MariBell project team through our website or at connect@maribelltransmission.com.
The permit applications, including the proposed route for the Gopher to Badger Link, have been filed with the Minnesota Public Utilities Commission. The applications will now move through Minnesota's regulatory review process, including opportunities for public input.
Dairyland Power Cooperative will submit a Certificate of Public Convenience and Necessity (CPCN) application to the Public Service Commission of Wisconsin (PSCW) for the MariBell Transmission Project this winter.
Following their independent reviews, the commissions will make the final decisions on the transmission line routes.
The proposed MariBell Transmission Project is being jointly developed by Dairyland Power Cooperative and GridLiance Heartland and would run approximately 140 miles between Marion, Minnesota, and Bell Center, Wisconsin. Dairyland and GridLiance Heartland are responsible for the development of MariBell, including routing, landowner and stakeholder outreach, permitting and, if approved, construction of the project.
BECI is a separate project with a different developer and its own development, permitting and stakeholder engagement processes. For information about BECI, including its route, design or project schedule, please contact the BECI project team.
The route development process included multiple stages of technical and environmental analysis, along with input from landowners, local governments, agencies, Tribal Nations and other community stakeholders. Potential routes were evaluated based on factors including existing transmission and utility corridors, proximity to homes and businesses, agricultural impacts, environmental resources, engineering requirements, safety and cost.
Community input was also an important part of route development in both states. The project teams hosted open houses, met with local officials and stakeholders, and provided additional opportunities to submit questions and comments as route options were developed and refined.
The route included in the Minnesota applications will now undergo independent regulatory review by the Minnesota Public Utilities Commission (MPUC).
Dairyland Power Cooperative will submit a Certificate of Public Convenience and Necessity (CPCN) application to the Public Service Commission of Wisconsin (PSCW) for the MariBell Transmission Project this winter.
Each state utilities commission governs the permitting process for the portion of transmission lines that traverses the applicable state (MN or WI), and each commission will review and approve the portion of the line that crosses its state.
Public Service Commission of Wisconsin (PSCW)
Minnesota Public Utilities Commission (MPUC)
Potential routes and alternatives were evaluated through technical and environmental studies, engineering analysis and community input. Factors included existing transmission and utility corridors, proximity to homes and businesses, agricultural impacts, roads and other infrastructure, wetlands and waterways, sensitive species, cultural and historic resources, safety and cost.
More than 95% of the proposed MariBell route would follow existing transmission corridors and rights-of-way, helping avoid the creation of a second major transmission corridor through the region.
The route included in the Gopher to Badger applications is a proposed route and is not yet final. In Minnesota, the MPUC will review the Gopher to Badger Link Certificate of Need and Route Permit applications. Dairyland Power Cooperative will submit a Certificate of Public Convenience and Necessity (CPCN) application to the Public Service Commission of Wisconsin (PSCW) for the MariBell Transmission Project this winter.
Both regulatory processes will include opportunities for additional public input before the commissions make final decisions on the transmission line routes in their respective states.
Drop us a Line
Do you have questions about the MariBell Transmission Project? Please email the team at connect@maribelltransmission.com.
Click here to follow us on Facebook.
.jpg?width=200&height=74&name=MariBell%20no%20company%20(2).jpg)