Route Development Process

The Regulatory Process

The route development process is a multi-step analysis that considers constraints, opportunities and alternatives that aim to minimize impacts to people and the environment.

1. Initial Landowner and Stakeholder Conversations


2.
Define Preliminary Route Options

  • Areas where viable routes can be located.

3. Refine Route Options We are here!

  • A further narrowed area within the preliminary route options

4. Proposed Route 

  • Develop proposed route(s) to submit to the Public Service Commission of Wisconsin (PSCW) and the Minnesota Public Utilities Commission (MPUC).

5. PSCW and MPUC review and issue a decision on project and route

Feedback from the community is a critical component of the route development process. We will incorporate comments from the public as well as other stakeholders, including:

Landowners

Local governments

Environmental agencies

Tribal Nations

Federal and state agencies

Additional Routing Considerations

During the routing process, our team will identify opportunities where routes and route alternatives could be located while evaluating sensitivities or areas that would create more impacts. Wherever possible, the proposed route will use existing transmission corridors to help minimize potential impacts.

During the routing process, our team carefully evaluates sensitive areas, resources and site-specific conditions that may require additional review and consideration:

| Agricultural impacts 
|
Airports
|
Alternative locations and routes
|
Cemeteries, religious facilities and cultural and historic resources 

| Existing transmission and utility corridors 
|
Forest 
|
Hospitals  
|
Impacts on sensitive animal and plant species 
|
Location of existing homes and businesses 
|
Pipelines 
|
Property, field and section lines 
|
Public recreational land 
| Rivers, lakes, streams and wetlands 
| Roads, highways and railways
| Schools, daycares and other buildings  

Stay Connected

Sign up for project updates to stay informed about how the MariBell Transmission Project will help power homes, farms and businesses across the Upper Midwest.

Drop us a Line

Do you have questions about the MariBell Transmission Project? Please email the team at connect@maribelltransmission.com.

Click here to follow us on Facebook.

©2025 Dairyland Power Cooperative and GridLiance Heartland LLC. All rights reserved.